Library Expansion and Renovation

Project Timetable



Relocate Library To Temporary Quarters

After extensive analysis it was determined that it would be more cost effective and much more pleasant for Library patrons, if the library moved completely out of the existing building during the renovation. The Library will relocate into a combination of new temporary space to be constructed over some of the tennis courts behind Roosevelt Extension and some gymnasium spaces in Roosevelt Hall. The newly constructed temporary space will then be available for use during the West Quad construction project. The relocation will be made in two phases, first into the Roosevelt Hall spaces, and then into the new temporary structure. The relocation has been planned and phased to maximize availability of Library services throughout the project.
  • Bidding and detailed design - October 1998 through January 1999
  • Library move-in to Renovated Roosevelt Hall spaces - May 1999
  • Library move-in to temporary structure - August 1999



Renovate and Expand Existing Library

  • Bidding - through March 1999
  • Exterior excavation and footings for new structures - March 1999 through July 1999
  • Library Move Out - Summer 1999
  • Demolition of interior spaces - through September 1999
  • Construction and Renovation - through July 2001
  • Library and Administrative Computing move-in to new building - Summer 2001